Project Merlin - Coors Brewery Burton On Trent

brewery installations

Contract value £500k.

Main Bottling Plant LV distribution.

Re-wiring of Cape Hill machines.

Commissioning of Cape Hill Machines.

De-Palletiser installation.

Puwer upgrade of Both Bottling and Canning machines.

Communications network.

High level Cable management and Stainless steel Droppers.

Upgrade of existing LV distribution Boards.

Bottling plant Small power installation.

All related Documentation.

Extraction of Bottling machines (20 off) from Cape hill-this included documenting of all cabling.

The electrical installation commenced 6 weeks late due to other trades and was completed 2 weeks ahead of program.

Savings made by Technical innovation £25k (Involved reusing existing LV cabling and changing duty in order to optimise plant whilst minimising cost).